Current Lead Time Status

In the past, our lead time communication was mostly focused production lead times. As indicated in the diagram below, this is the estimated time between order acknowledgement and shipment. These lead time estimates did not include the time to schedule deliveries or the time between the product departing our facilities and reaching the final ship-to address. We will continue to provide you with up to date production lead times, which are estimated with high accuracy.

Additionally, the entire building products industry is impacted by significant fluctuations in demand as well as delays and constraints with freight and cross docks. To better provide you visibility into how these may affect your orders, we are now providing estimated total lead times which are inclusive of the time to schedule home deliveries, production time, and the time to reach the final destination.

Current Lead Time Status
Actual lead times can vary from the stated lead time in regions where logistical challenges are significant.

Rotate Your Phone Please

For best experience
rotate your device to “landscape” mode,
or view this page on a larger screen
such as tablet or laptop.

 

BRAND

STANDARD
PRODUCTION
LEAD TIME

EXTENDED
PRODUCTION
LEAD TIME

 

ESTIMATED
TOTAL
LEAD TIME

  Cabinets2000 6 Weeks None   6-7 Weeks
  Design-Craft 4 Weeks +13 Weeks   18-19 Weeks
  KraftMaid 3 Weeks +6 Weeks   10-15 Weeks
  Master WoodCraft 3 Weeks None   3-4 Weeks
  MasterCraft 3 Week None   4-5 Weeks
  Medallion Silverline 3 Weeks +14 Weeks   18-19 Weeks
  Medallion Gold, Platinum, Bath Silhouettes 4 Weeks +13 Weeks   18-19 Weeks
  Merillat Masterpiece 3 Weeks +6 Weeks   10-15 Weeks
  Merillat Classic – Eastern Region 2 Weeks +29 Days   8-9 Weeks
  Merillat Classic – Central/West Region 2 Weeks +20 Days   6-7 Weeks
  Merillat Basics 8 Days +35 Days   7-8 Weeks
  QualityCabinets – Eastern Region 2 Weeks +29 Days   8-9 Weeks
  QualityCabinets – Central/West Region 2 Weeks +20 Days   6-7 Weeks
  QualityCabinets WoodStar 8 Days +35 Days   7-8 Weeks
  Serenade 4 Weeks +12 Weeks   17-18 Weeks
  Smart 3 Weeks +13 Weeks   16-17 Weeks
  Yorktowne Classic 3 Weeks +14 Weeks   18-19 Weeks
  Yorktowne Iconic, Historic, Bath Sanctuary 4 Weeks +13 Weeks   18-19 Weeks
   
Current Lead Time Status

Partner with us.

Whether you’re with a Kitchen & Bath showroom, a builder, an architect or a specifier for multi-family properties, let’s build life into the kitchen – together.

The kitchen is where we live life.
And at Cabinetworks, it’s what we live for.

Current Lead Time Status